From FLTF: The Michigan Court of Appeals scheduled an oral argument for Heron Cove Association's claim of appeal for December 11, 2024, in Lansing. Learn more about the Court of Appeals here. The judges will not make a ruling during this session. They will listen to both parties, ask questions, and issue their opinion or order at a later date. There is no time limit for issuing their opinion or order.
The latest construction update newsletter has also been posted to the Four Lake Task Force website. Construction has halted at all but the Sanford Lake Dam. The concrete pouring has been completed on all five piers and the low-level outlet walls. Permitting work is ongoing for the final restoration permit for Edenville Dam and is still expected by the end of the year. Work is planned to suspend on Sanford Dam at the end of January 2025.