Apr 27, 2026 ∙ 1 min
FLTF Construction New Update
Four Lakes Task Force has posted the most recent construction update summarizing the activity at each dam. As most people know, the Sanford Dam is substantially complete and is full to the winter level, at this time. Each dam is running within budget and hitting quality performance indicators. Only Smallwood and Secord are running a bit behind schedule. To read the full April News click here. Future events from FLTF include: May 13 Introduction to Natural Shorelines Webinar from 6-8:00 pm...
10
0
Feb 25, 2026 ∙ 1 min
FLTF Informational Webinar March 4
Please join the Four Lakes Task Force for an informational webinar on March 4, 2026 at 5:00 pm. Click here to register.
16
0
Feb 14, 2026 ∙ 1 min
Sanford Dam Substantially Complete
The words we've all been waiting to hear!! According to the February FLTF news update: "Sanford Dam: Sanford is now considered substantially complete with all major restoration work finished. Despite substantial completion occurring six weeks later than anticipated, we still expect to begin to start the lake refill process on April 15 (pending inspections and permits)." To read the full news update at the FLTF website, click here .
22