All Work to Stop by End of Year

According to the latest update from FLTF, even though the judge granted the motion to expedite the briefing schedule - the process will not be completed by the end of September. Consequently, all work will be suspended on the three remaining dams under construction.

  • Secord will be suspended in October

  • Smallwood will be suspended in September

  • Edenville construction was suspended in June

  • Sanford will be suspended in January


Please link to the full update for details.

 
 
 

Recent Posts

See All
FLTF Construction New Update

Four Lakes Task Force has posted the most recent construction update summarizing the activity at each dam. As most people know, the Sanford Dam is substantially complete and is full to the winter lev

 
 
 