top of page

Roller Compacted Concrete (RCC) Work on Sanford Requires Extended Hours

Crews are beginning to place roller compacted concrete along the Sanford Dam embankment for the auxiliary spillway. This activity requires extended work hours and additional traffic.
Beginning September 22 and lasting until around Thanksgiving, the crews will work from approximately 6:00 AM to 6:00 PM Monday through Saturday. A small night crew and Sunday crew will also be on site. During the Monday through Saturday timeframe, approximately 30 trucks of materials each day will be delivered to the site, entering from the W. Irish Street site entrance.
Please contact FLTF with any questions or concerns.

 
 
 

Recent Posts

See All
Golf Cart Winner Announced!

Congratulations Greg Crawford on winning our golf cart raffle! Thank you to everyone who purchased tickets for our raffle! The raffle...

 
 
 

Comments


bottom of page